Supplemental Data

1. Rated loads included in the charts are the maximum

allowable freely suspended loads at a given boom

length, boom angle and load radius, and have been

determined for the machine standing level on firm

supporting surface under ideal operating conditions.

The user must limit or de-rate rated loads to allow for

adverse conditions (such as soft or uneven ground,

out-of-level conditions, wind, side loads, pendulum

action, jerking or sudden stopping of loads,

inexperience of personnel, multiple machine lifts, and

traveling with a load).

2. Rated loads do not exceed 75% of minimum tipping

loads. Rated loads based on factors other than

machine stability such as structural competence are

shown by asterisk * in the charts.

3. The machine must be reeved and set-up as stated in

the operation manual and all the instruction manuals if

these manuals are missing, obtain replacements.

The crane must be leveled to within 1% on a firm

supporting surface.

Boom backstops are required for all boom length.

Gantry must be fully raised position for all

operations.

4. Do not attempt to lift where no radius on load is listed

as crane may tip or collapse.

5. Attempting to lift more than rated loads may cause

machine to tip or collapse. Do not tip machine to

determine rated loads.

6. Weight of hooks, hook blocks, slings and other lifting

devices are a part of the total load. Their total weight

must be subtracted from the rated load to obtain the

weight that can be lifted.

7. When lifting over boom point with jib or auxiliary

sheave, rated loads for the boom must be deducted

as shown below.

Jib Length (ft)

Aux.

30'

40'

50'

60'

70'

Deductions (lbs)

700

2,400 3,200 4,200 5,200 6,200

When auxiliary sheave is used for 10 or 9 reeving

parts of line, it is not required to deduct 700 lbs from

the rated load.

8. The total load that can be lifted by jib is limited by

rated jib loads.

9. Boom lengths for jib mounting are 90 ft (27.4 m) to

200 ft (61.0 m)

10. The total load that can be lifted by the auxiliary

sheave is the value for 700 lbs deducted from rated

load for the boom (without auxiliary sheave installed);

however, the auxiliary sheave rated load should not

exceed 24,000 lbs.

11. Boom lengths that can attach auxiliary sheave are from

50 ft (15.2 m) to 220 ft (67.1 m).

12. The boom should be erected over the front of the

crawlers, not laterally. When lifting from or lowering to the

ground the boom length of 230 ft (70.1 m) and the boom

length of 200 ft (61.0m) with jib, the blocks for erections

must be placed at the end of the crawlers.

13. Least stable position is over the side.

14. Maximum hoist load for number of reeving parts of line for

hoist rope.

Main Boom Hoist Loads

No. of Parts of Line

1

2

3

4

5

Maximum Loads (lbs)

25,000

50,000

75,000

100,000

125,000

No. of Parts of Line

6

7

8

9*

10*

Maximum Loads (lbs)

150,000 175,000 200,000

225,000

240,000

* - Use auxiliary sheave

Jib Hoist Loads

No. of Parts of Line

1

Maximum Loads (lbs)

24,000

Auxiliary Hoist Loads

No. of Parts of Line

1

2

Maximum Loads (lbs)

25,000

50,000

15. Assembling the counterweight

76300 lbs counterweight (No.1 ~ No. 5)

14,300 lbs carbody weight

16. Weight of recommended hook block

Hook Block 120USt

77USt

39USt Ball Hook

Weight (lbs) 3,750 1,990 1,545 1,000

If the weight of the hook block to be used is lighter than the

recommended weight, the jib may turn over backward or it is

difficult to lower the empty hook block.

17. Rated loads listed apply only to the machine as originally

manufactured and designed by KOBELCO CONSTRUCTION

MACHINERY CO., LTD. Modifications to this machine or use

of equipment other than that specified can reduce operating

capacity.

18. Designed and rated to comply with ANSI Code B30.5.

Operation of this equipment in excess of rated loads or

disregard of instruction voids the warranty.